What’s on the machining estimate template
| Item | Qty | Rate | Amount |
|---|---|---|---|
| Setup and programmingOne-time | 1 | $450.00 | $450.00 |
| CNC machiningPer part, 0.35 h at $95/h | 100 | $33.25 | $3,325.00 |
| Material, 6061-T6 aluminumPer part | 100 | $6.80 | $680.00 |
| Anodize, clearPer part, outside vendor | 100 | $3.50 | $350.00 |
| Inspection and first article | 1 | $150.00 | $150.00 |
| Estimated total | $4,955.00 | ||
Example prices in US dollars. Replace them with your own; in the generator, any currency works.
Estimating machined parts
Separate one-time costs (programming, setup, fixtures, first-article inspection) from per-part costs (cycle time, material, finishing). That makes quantity breaks easy to show: per-part price falls as setup spreads across more parts. Reference the drawing and revision, the material, tolerances and finish. State the lead time from purchase order.
Frequently asked questions
How do I show quantity breaks?
Give unit prices at several quantities, such as 10, 100 and 500, with setup spread across them.
Should setup be separate?
Yes, on first orders; repeat orders may not need it.
What if the drawing changes?