What’s on the bathroom remodel estimate template
Extra fields on this template: Job site.
| Item | Qty | Rate | Amount |
|---|---|---|---|
| Demolition and disposalFull gut, 5 × 9 ft | 1 | $1,500.00 | $1,500.00 |
| Plumbing, relocate drainLicensed plumber | 1 | $2,400.00 | $2,400.00 |
| Walk-in showerWaterproofing, pan, glass door | 1 | $4,800.00 | $4,800.00 |
| Floor and wall tileAllowance $7/sq ft material | 1 | $3,600.00 | $3,600.00 |
| Vanity, toilet and fixturesAllowance | 1 | $2,200.00 | $2,200.00 |
| Permit and contingency, 10% | 1 | $1,600.00 | $1,600.00 |
| Estimated total | $16,100.00 | ||
Example prices in US dollars. Replace them with your own; in the generator, any currency works.
What drives a bathroom remodel estimate
- Layout changes: moving a toilet or drain costs far more than replacing in place.
- Tub to walk-in shower: waterproofing, a new pan and glass add up.
- Tile: price per square foot of material plus installation; large-format and patterns take longer.
- Allowances for vanity, toilet, faucets and lighting until the client chooses.
- Hidden damage: rot and leaks under old floors are common. Price repairs separately.
For kitchens, see the kitchen remodel estimate template.
Frequently asked questions
How much contingency for a bathroom?
10% is common, more in older homes with original plumbing.
Does a bathroom remodel need a permit?
Usually, if plumbing, electrical or walls change. Check with your local building department.
How long does a bathroom remodel take?
Often two to four weeks for a full gut, depending on inspections and tile work.